START-FINISH RULE title: start-finish rule (PS) (SAP Library - Glossary)
START-FINISH RULE category: Project System (PS)
START-FINISH RULE explained:

A measuring technique for determining the percentage of completion in progress analysis.

When the start-finish rule is used in progress analysis, the percentage of completion (POC) increases from 0% to the initial POC at the start date. When the finish date is reached, the POC is 100%.

Values used in the start-finish rule are:

0 - 100: The initial POC is 0 %. 20 - 80: The initial POC is 20% 50 - 50: The initial POC is 50 %

You can use the start-finish rule to estimate how the project is progressing. You must only use it to perform analyses for the whole project structure.

More terms such as start-finish rule in Dictionary S.

Manual Set Of Hits:
Help A set of specifications that fulfills certain search criteria start-finish rule definition.
Manual Selection Include:
Help Include program within a logical datanbase in which the standard selection screen of the logical database is defined start-finish rule explain.
Manual Service Interval Grouping:
Help grouping of waste disposal services for containers or cleaning objects. This enables you to control the supply of values in Billing. Service interval grouping can only be carried out for the same start-finish rule what is.
Manual Selection Method (IS-HER-CM):
Help A method used to select a specific set of objects based on a predefined procedure start-finish rule meaning.
Manual SAP For Higher Education & Research:
Help solution that provides universities and research institutions with integrated software tools to facilitate research, teaching and study, as well as to manage core processes of administration start-finish rule abbreviation.
  • Dodano:
  • Autor: