CONSTRAINT-BASED PLANNING title: constraint-based planning (SCM-APO) (SAP Library - Glossary)
CONSTRAINT-BASED PLANNING category: Advanced Planning and Optimization (SCM-APO)
CONSTRAINT-BASED PLANNING explained:
A form of production planning which is based on the assumption that the whole production process is determined by certain bottlenecks. Possible bottlenecks that have a crucial influence on production are:
- Resources with low capacity
- Raw materials that are only available in limited quantities
The bottlenecks are planned in constraint-based planning with special attention. A resource with low capacity is planned with priority. Planning of all remaining resources is dependent on the planning results of this work center.
More terms such as constraint-based planning in Dictionary C.
- Manual Churn Management:
- Help Influencing customer turnover in a company with the aim of reducing the frequency of switches to competitors by building up customer loyalty constraint-based planning definition.
- Manual COA Company Code:
- Help Third party management A company code in which you map the real estate objects and processes of a condominium owners' association (COA constraint-based planning explain.
- Manual Correlation (EP):
- Help A procedure used to define the relationships between business objects and transactions in the two systems constraint-based planning what is.
- Manual Certificate Of Deposit:
- Help A money market instrument issued by banks that has a set maturity date. Maturities can range from a few weeks to several years constraint-based planning meaning.
- Manual Combining Character Sequence:
- Help Character sequence consisting of either a base character followed by a sequence of one or more combining characters, or a sequence of one or more combining characters constraint-based planning abbreviation.